I use MS Project Server 2010 in farm envrionment with this CU 14.0.6126.5001
I have a query that gives me remaining work and resource capacity. Strangely data in this table stop at 2014-02-28 00:00:00.000 (note that we are 2013-06-13). I only have data for next 260 days (~8month)...
I change te setting in PWA -> Additional Server Settings ->Resource Capacity Settings -> * <label for="ctl00_ctl00_PlaceHolderMain_PWA_PlaceHolderMain__resSection_ctl01__monthsAhead">Months ahead:</label>24.
But nothing change.
Any clues?
Thanks
PWAdmin