IIf([% Complete]<100,switch(([Finish Variance])<=0,"Green",([Finish Variance])>0 And [Total Slack]>5,"Yellow",([Finish Variance])>0 And [Total Slack]<=0,"Red"),"Complete")
We have built in a Milestone RAG Custom field using the above formula, but for some reason it is only picking up delayed Milestones with 0 days total slack as Red.
I need for it to pick up Milestones that have finish variance greater than 0 & Total Slack between 0 & 5