Are records in AssignmentByDay replaced or added to when Resource Task Updates are made

$
0
0

We are using a combination of MY Timesheets and Task Updates to implement a PM-approved time sheet system. See http://social.msdn.microsoft.com/Forums/en-US/a958a106-2a80-4f3f-9a9f-eb0ae53e5774/which-tables-are-updated-when-a-pm-accepts-task-updates-or-how-to-have-timesheets-with-pm-approval?forum=project2010custprog

We have turned on Protected Actuals so that actuals may only be updated by resource input.

However the table of Task Updates (MSP_EPMAssignmentByDay) already had actuals created by PMs. So our approach was to treat all of the records pre-“Protected Actuals” as a starting point that we could subtract from the current state of records to get the hours added by task updates.

However it appears that where a resource had time assigned to them post-“Protected Actuals” that time is replaced rather than added to. We have only seen this in live and only with one user so far (the rest did not have pre-existing future actuals). But what behavious should we expect? Is it documented anywhere. I think we can deal with it either way – as long as it is consistent.

MikeCro


Mike