Quantcast
Channel: Project Customization and Programming forum
Viewing all articles
Browse latest Browse all 5347

Custom formulas

$
0
0

IIf([Baseline Start]=projdatevalue("NA"),0,IIf([% Complete]=100,1,IIf([Finish]<[Current Date],4,IIf([Finish Variance]>0,4,IIf([Duration9]/480<11,3,IIf([Duration10]/480<11,3,2))))))

0(QUESTION MARK) - not baselined

1(BLUE) - complete

2(GREEN) - on track, starts later than 2 weeks out from the current date

3(YELLOW) - on track, in progress or starts/finishes within 2 weeks

4(RED) - finish date in the past, or task is incomplete with a planned finish later than the baseline finish


Viewing all articles
Browse latest Browse all 5347

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>