Hi.
I have a file that has a single task. its fixed duration and is not effort driven and no resource is defined. duration is set to10 days. after5 days, %complete is10%. after entering this data and rescheduling, in MSP2007 duration and %complete remain constant (10%and 10days), while in MSP2010 %complete decreases to7% and duration increases to14 days.Why??
Another question: I set task type as fixed unit and other conditions remain constant as described befor, after rescheduling in MSP 2010, task will split and finish date changes. (for example increases4 days). Problem happens when I copy %complete column on itself. In this case, finish date returns to its original value (decreases4 days.)