Hi,

I have a customer who wants project managers to work with PWA (2010 version) instead of project professional.

They ask if a functionality can be developed (I guess, by using PSI) and attached to a button in the PWA ribbon for the following Pro functionalities:

  • Mark on Track (when clicked - the progress bar adjusts to the project current/status date)
  • Move Incomplete parts to begin after status date
  • Move Complete parts to end before status date

Thanks,