I am trying to generate Microsoft Project XML. Everything seem to import correct in Project apart from % Complete on tasks. I have set task start, finish, early start, finish, late start finish, PercentComplete, duration, actual duration, remaining duration, TimephasedData for each day.
I can see it is all exported correctly in XML however when I import into Microsoft Project, it changes % Complete.
I am using formula given on http://office.microsoft.com/en-gb/project-help/percent-complete-fields-HP001024590.aspx to calculate % Complete but it does not seem to work?
Can anyone please tell me how does it calculate % Complete, % Work Complete, PhysicalPercentComplete please, or if you can provide me where I can read about each field in XML and how it is calculated or effects other fields while importing in MS Project it would be great help.
Vinayak
Vinayak Nirvani.