EPM server 2010 task page - "An unknown error has occurred"

$
0
0

Hi All,

Please note that I am using EPM server 2010.

We have created various set of task in MPP and have saved and published it.

Once the user login with his/her credential to EPM 2010 account. He/She can see assigned task in her timesheet.

After entering actual hrs in timesheet user save timsheet.

But once he/she clicks on Task button to Import the status of task. The task page is giving an error message "An unknown error has occured".

I made all possibel changes and setting to resolve this issue. But still I am failed to find an answer.

Please help me to find the correct resolution.

Regards,
Prashant Phate