Hello,
We are using Project Server 2010 in SEM mode, and we use Timesheet for all the Project Progress. We recently migrated directly from 2003 to 2010. The Timesheet Grid in 2010 yes does eliminates the controls installation on client machines, but our users are not liking because of following:
- In 2003, Timesheet showed Projects and Tasks most like the Gantt Chart Table... Grouped by Project > Summary Tasks > Tasks. In 2010, I have to add 3 fields to get the closest look but group by Project, to distinguish the "same name" tasks by adding "Task Hierarchy", and to sort it in the order of Task Index used WBS... even after doing all 3 fields, the sorting on wbs failed because... it sorts like Text type... for example it sorts like this: 1.0, 1.10, 1.1,1.2 etc... that loses the interest of the new user coming from 2003.
Any suggestions on how to customize the grid to make it more user friendly? the task layout like in 2003?
Thank you.
Regards,
Kishore Dodda