Task BCWS vs. Resource BCWS

$
0
0

I have a VBA program that picks up the BCWS from each task and processes it. The values being retrieved are not what I expected. The screen shot below illustrates the problem. I enter Actual Work in the Resource Usage view, and it produces the correct BCWS for the associated resource. The BCWS I'm picking up from the task, however, is a different value. How do I get the value entered for the resource? Alternatively, how do I force the task to have the correct value?

Example: see Tsk01, period 3. The rate for R1 is $100/hr. The $3,200 that appears against the resource is correct. The $3,750 that appears against the task is incorrect and is causing the program to produce misleading results.

 


RobVV