Assigning Resources to tasks

$
0
0

Hello, I am new to MSP, and have a "naive" question: I have a task that last 8 weeks.  I have approximately 6 resources that need to be assigned to that task, but not for the entire 8 weeks.  How do I assign one resource for 1 week, another for 3 weeks, and so on?

Thank you for any help you provide!

Christine