I am creating a Project file by importing a CSV file. I need to be able to import both the real Actual Work hours and the real Actual Finish dates contained in the CSV file. Somehow Project ties these two together for finished Subtasks:
entering the Actual Work sets the Actual Finish. And entering the Actual Finish clears the Actual Work.
Is there a sequence to enter those for a Subtask, and display what is in the CSV file, rather than what Project wants to compute?
↧
Need to Enter Real Subtask "Actual Work" and "Actual Finish"
↧