Re-allocating Actual Costs and Actual Work from one project to multiple projects

$
0
0

My company would like to track costs in one project and then re-allocate those costs to multiple projects.  Example: An end user would submit a timesheet against a task named 'Analysis' for Project A.  Once accepted and published, the costs for those hours would be subtracted from Project A and 60% of those costs would be transferred to the 'Analysis' task for Project X and 40% of the costs for those hours would be transferred to Project Y. 

We believe we can accomplish this through reporting, but before we go this route, we wanted to make sure there was not a logical, supported way in MS Project Server to complete these actions.  Could a script be developed to accomplish this?

Thank you!

Tasha


Viewing all articles
Browse latest Browse all 5347

Latest Images

Trending Articles



Latest Images

<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>