Updating task custom fields

Hi , 

I want to update the taskcustom field present in the project using psi , but i am able to update only one value in task and remaining tasks are not getting updated and its showing empty in the task custom field . 

For example - I have a project with 10 tasks and all the tasks have resource name assigned , If resource name = "test " then that particaular resource name should also get updated in the task custom field (named as "specific resource ) .

if resource name != "test" then no update will be done . 

At present if task1, task3, task 7 having a resource name "test " the task custom field (specific resource ") is getting updated only for task 1 and in 3 & 7 its showing empty . 

 help me how to do it 

Regards

Indresh 