Project Server 2010 running in single entry mode.
We have an SSRS report which shows the user a preview of their pending timesheet approvals and as part of this we want to show the remaining work value 'New' and 'Old'.
ie. we show what the remaining work is now, and what the remaining work will be if timesheet updates are approved.
This works perfectly when the remaining work is calculated by the system, as in the user enters time against the task and remaining work is automatically adjusted. It does NOT work when the user submits a new value of remaining work manually, via their timesheet.
Where does this bit of data go? I have searched PWA_Reporting and cannot find this value.