Dear All,
There is one case where projects published on PWA 2013 through MS Project Professional. But during that period, Predecessors was not aligned in those projects and some of Task info not available (Start Date,end date etc). Now we have to align predecessors in PWA for those projects. Here issue is like whenever we are aligning Predecessors in PWA for Projects then Task dates get changed as some of task not having date (Old Data) nd some task having dates.
Is there any way by which we can restrict changing of dates for already filled Task information in PWA 2013 (Project Server)?