We are currently testing the single entry mode, and we want to understand more about this model.
During the testing, we found the timesheet entry impacts much on the project plan. For example,
Supposed the start / end date for the assignment is from 10/1 to 10/20, but if the user starts report hours on 10/10, the end date may be shifted to 10/30 or other date. And sometime the end date may be shorten to an eailer date (e.g. 10/18).
Is that any document describing the exact behavior on how the timesheet will impact the project plan (start/end date, work, remaining work etc.)
in our organization, we enable "auto-approval" for timesheet and timesheet lines, that means no approval before the timesheet data is populated into the project plan.
Can we archive the goal - the start / end date is never shifted due to the timesheet submission.
Kevin Li