Hi, between two tasks in need to give 3 days gap, is there a way to set the same automatically for eg: Task 1 ends on Dec 07, 2014, task 2 should start on Dec 10, 2014. However task 2 has dependency on task1 and it will start only once task1 is finished. I dont want to do set dates manually for task 2.