I want to set a Predecessor on Task 2 using CSOM code. The predecessor is "1FS + 10days"
I am currently stuck as i can't find any way of setting "Lead time" using CSOM.
This is page from MSDN on DraftTaskLink Class
http://msdn.microsoft.com/en-us/library/microsoft.projectserver.client.drafttasklink_di_pj14mref_members(v=office.15).aspx
On the other hand, it seems possible (not too sure though) through PSI
http://msdn.microsoft.com/en-us/library/websvcproject.projectdataset.dependencyrow_di_pj14mref_members(v=office.15).aspx
Is this a limitation of CSOM ? If so, is there a documentation which specifically mention this ?
Hammad Arif EPM Advice Blog