Hi,

The Project Server is not considering the Finish Date field of a task created in TFS. It's important because in my process model the start and finish date must be defined (first time) from a TFS task.

The PS TFS integration was done correctly and has also changed the mapping of theStart Date and Finish Date fields removing the propertyonConflict = "PsWins" (http://msdn.microsoft.com/pt-br/library/gg412658.aspx). However, when I create a task in TFS, only theStart Date is being published in PS. The PS is disregarding the Finsh Date defined in task.

The inverse process, task created from PS to TFS, works fine.