It seems that the work hours and Percent complete are tied together (for updating tasks). is there a way to remove this feature?
I tried looking into the enterprise custom fields, but since it is a part of project OOTB, it is not there. is there another place i can find and change this?
or perhaps a workaround?
for example, i have 1 person assigned to a single 8 hr task, due to some unforeseen circumstance, he has worked 6 hours and is only 50% done, however, when he goes to his tasks to update his work, he can not enter both of these at the same time.
he can either update to 50% done (4 hrs filled in automatically )
or he can enter 6 hours worked (75% done filled in automatically, overriding his 50% done if entered)