Hello Everybody,
I am new to Project and I am having a REALLY hard time figuring out ONE thing!
I have all of the dates for our project put in and it appears to the right on the Gantt chart.
After entering all the main timeline dates, I needed to add days that were non-working and holidays, which I did by entering them in the Change Working Time option and saved them.
My question, that I cannot seem to find anywhere is, HOW do I get those non-working dates to appear on the chart to the right so my boss can see them along with the tasks?
I have gone into timescale and chosen a color and pattern, but they still do not show up there??
Is this not a possibility?