Hello,
I'm using MS Project 2010 to manage little projects and confronted with little problems.
What I want :
the main goal is to follow the real production so i need to have a fixed start date and a fixed end date but when i change the work of the task or the ressource allocations hours, the dates and % work complete are moving. => How to disable it.
with this kind of tiny projects, i need to manage manually those tasks so how to disable the "auto schedule / auto calcultaion" functionnality ? (the tasks are manually scheduled)
thanks a lot
Kevin