"Move Incomplete Parts to Status Date" versus "Reschedule Work to start after status date:"

$
0
0

Is there a difference between "Move Incomplete Parts to Status Date" which is in the Tasks group of the Task Ribbon, and "Reschedule Work to start after status date:" which found in the Status group of the Project ribbon tab?

I ask because it seems that at one time or another, one of these functions does not work as expected in moving the remaining work past the status date for a particular (same) task.


\Spiro Theopoulos, Montreal, QC (Canada)