Sorting grouped tasks in MS Project 2010

$
0
0

Dear Forum,

I created a view and grouped the tasks in MS Project 2010. The following problem comes up: As I can only change between "ascending" and "descending" while creating the Group, all my tasks sort alphabetically but I want to have them arranged in chronological order. When I try to sort them, they stay as they are.

One solution I could think of would be to add for example numbers in front of my tasks (e.g. 1_task1, 2_task2..) so Project would arrange them accordingly but that would not look nice, neither would I have to Change it manually each time.

Another solution would be to create a custom field including the sequence and then Group my tasks accordingly but I was wondering if any of you folks know any smart solution to this problem?

Regards,

Heiner