Hi experts,
We have a requirement to make tasks 100% complete once it becomes greater than 0% by team members. Currently I modify task % complete from Project 2013 Professional and publish to Project 2013 Server.
Can I make this automatic?
I thought about following options but I'm not sure if this is technically feasible. Any opinion is welcomed!
- Option A: Set SQL server trigger to task percent complete column
- Option B: Run shell script to run PSI-based web service to update task percent
The situation is somewhat similar to this thread.
https://social.technet.microsoft.com/Forums/en-US/4e9af917-637f-4321-a689-ea294d2988ec/how-can-2-resources-update-a-task-using-pwa-and-not-having-the-work-complete-being-split?forum=projectserver2010general