Hi All,
I am facing an issue in EPM / Project Server 2010.
When I update project property (enterprise custom field information) using PSI and update Project details using PDP.
Percentage of some project revert back from 100% to 99% and I am using of formula field it will become null after update project information as I mentioned above that either PSI or by PDP both.
Thanks & Regards,