In Project Pro 2010, I have created a custom field with a lookup table and graphical indicator. Despite
altering all the settings on the graphical indicator page, including checking and un-checking the inherit criteria, I cannot get the drop-down to display on anything but the summary tasks. The lookup list does not display in the sub-task fields and If I try
and manually enter in that custom field in a sub-task it crashes the program. When I click the radio buttons under graphical indicators, it shows the same information in my rows. Any ideas on how to correct this or if it is possible?
↧