Hi,
Task Name | Start | Finish | Outline Level |
Program Local - SED | Thu 20.03.14 | Mon 13.11.17 | 1 |
PK Phase 1 | Thu 20.03.14 | Thu 20.03.14 | 2 |
PK Phase 2 | 2 | ||
PK Phase 3 | Thu 20.03.14 | Thu 20.03.14 | 2 |
PK Phase 4 | Thu 20.03.14 | Thu 20.03.14 | 2 |
PK Phase 5 | Thu 20.03.14 | Thu 20.03.14 | 2 |
PK Phase 6 | Thu 20.03.14 | Thu 20.03.14 | 2 |
KR Phase 1 | Mon 07.04.14 | Fri 23.01.15 | 2 |
KR Phase 1 - 1 | Mon 07.04.14 | Mon 05.05.14 | 3 |
KR Phase 1 - 2 | Mon 21.04.14 | Mon 05.05.14 | 3 |
KR Phase 1 - 3 | Mon 05.05.14 | Mon 19.05.14 | 3 |
KR Phase 1 - 4 | Mon 19.05.14 | Mon 26.05.14 | 3 |
KR Phase 1 - 5 | Fri 28.11.14 | Fri 16.01.15 | 3 |
KR Phase 1 - 6 | Fri 09.01.15 | Fri 23.01.15 | 3 |
The above Table shows my task distribution.Here I want to find tasks with suffix "SED" and then find a outline level 2 task and check whether it has subtask (outline level 3) if it has no outline level 3 task then that particular outline level 2 task has to be deleted.
Any suggestions?