Oh, smart ones!
I am wanting to create a project template were the tasks are needing to start each new working day within the week. However the task duration are less then 3 hrs long. The Tasks are dependent upon the other yet are not recurring tasks.
Example:
Task 1 - Duration 1.5 hrs (Fixed Unit) (2 resources & 1 equipment resource)
Task 2 - Duration 1.2 hrs (Fixed Unit) (2 resources & 1 equipment resource)
Task 3 - Duration 2 hrs (Fixed Unit) (2 resources & 1 equipment resource)
Tasks must start on the next new working day.
Multiple tasks are not able to be completed same day. I want to create a template and would like to avoid creating individual task constraints or lag times. Since I will be replicating this project over and over on different Project Start Dates. Total Tasks will be around 100 tasks.
Thank you for your time, help, and direction