I am trying to change the current Opened (Active) Project using the XML Import and “Merge Data into the Active Project” option
Initially Project is as follows
<Image1 >
This project contains 3 tasks Task 1, Task 2 and Task 3
Following is the XML created for this project
<?xml version="1.0" encoding="UTF-8" standalone="yes"?><Project xmlns="http://schemas.microsoft.com/project"><SaveVersion>14</SaveVersion><Name>ProjectImportTest.xml</Name><Title>ProjectImportTest</Title><Company>c</Company><Author>Author, Project</Author><CreationDate>2015-08-26T08:00:00</CreationDate><LastSaved>2015-08-31T11:43:00</LastSaved><ScheduleFromStart>1</ScheduleFromStart><StartDate>2015-08-26T08:00:00</StartDate><FinishDate>2015-09-22T17:00:00</FinishDate><FYStartDate>1</FYStartDate><CriticalSlackLimit>0</CriticalSlackLimit><CurrencyDigits>2</CurrencyDigits><CurrencySymbol>$</CurrencySymbol><CurrencyCode>USD</CurrencyCode><CurrencySymbolPosition>0</CurrencySymbolPosition><CalendarUID>1</CalendarUID><DefaultStartTime>08:00:00</DefaultStartTime><DefaultFinishTime>17:00:00</DefaultFinishTime><MinutesPerDay>480</MinutesPerDay><MinutesPerWeek>2400</MinutesPerWeek><DaysPerMonth>20</DaysPerMonth><DefaultTaskType>0</DefaultTaskType><DefaultFixedCostAccrual>3</DefaultFixedCostAccrual><DefaultStandardRate>0</DefaultStandardRate><DefaultOvertimeRate>0</DefaultOvertimeRate><DurationFormat>7</DurationFormat><WorkFormat>2</WorkFormat><EditableActualCosts>0</EditableActualCosts><HonorConstraints>0</HonorConstraints><InsertedProjectsLikeSummary>1</InsertedProjectsLikeSummary><MultipleCriticalPaths>0</MultipleCriticalPaths><NewTasksEffortDriven>0</NewTasksEffortDriven><NewTasksEstimated>1</NewTasksEstimated><SplitsInProgressTasks>1</SplitsInProgressTasks><SpreadActualCost>0</SpreadActualCost><SpreadPercentComplete>0</SpreadPercentComplete><TaskUpdatesResource>1</TaskUpdatesResource><FiscalYearStart>0</FiscalYearStart><WeekStartDay>0</WeekStartDay><MoveCompletedEndsBack>0</MoveCompletedEndsBack><MoveRemainingStartsBack>0</MoveRemainingStartsBack><MoveRemainingStartsForward>0</MoveRemainingStartsForward><MoveCompletedEndsForward>0</MoveCompletedEndsForward><BaselineForEarnedValue>0</BaselineForEarnedValue><AutoAddNewResourcesAndTasks>1</AutoAddNewResourcesAndTasks><CurrentDate>2015-08-31T08:00:00</CurrentDate><MicrosoftProjectServerURL>1</MicrosoftProjectServerURL><Autolink>0</Autolink><NewTaskStartDate>0</NewTaskStartDate><NewTasksAreManual>1</NewTasksAreManual><DefaultTaskEVMethod>0</DefaultTaskEVMethod><ProjectExternallyEdited>0</ProjectExternallyEdited><ExtendedCreationDate>1984-01-01T00:00:00</ExtendedCreationDate><ActualsInSync>0</ActualsInSync><RemoveFileProperties>0</RemoveFileProperties><AdminProject>0</AdminProject><UpdateManuallyScheduledTasksWhenEditingLinks>1</UpdateManuallyScheduledTasksWhenEditingLinks><KeepTaskOnNearestWorkingTimeWhenMadeAutoScheduled>0</KeepTaskOnNearestWorkingTimeWhenMadeAutoScheduled><OutlineCodes/><WBSMasks/><ExtendedAttributes/><Calendars><Calendar><UID>1</UID><Name>Standard</Name><IsBaseCalendar>1</IsBaseCalendar><IsBaselineCalendar>0</IsBaselineCalendar><BaseCalendarUID>-1</BaseCalendarUID><WeekDays><WeekDay><DayType>1</DayType><DayWorking>0</DayWorking></WeekDay><WeekDay><DayType>2</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>3</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>4</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>5</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>6</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>7</DayType><DayWorking>0</DayWorking></WeekDay></WeekDays></Calendar></Calendars><Tasks><Task><UID>0</UID><ID>0</ID><Name>ProjectImportTest</Name><Active>1</Active><Manual>0</Manual><Type>1</Type><IsNull>0</IsNull><CreateDate>2015-08-26T17:23:00</CreateDate><WBS>0</WBS><OutlineNumber>0</OutlineNumber><OutlineLevel>0</OutlineLevel><Priority>500</Priority><Start>2015-09-15T08:00:00</Start><Finish>2015-09-22T17:00:00</Finish><Duration>PT48H0M0S</Duration><ManualStart>2015-09-15T08:00:00</ManualStart><ManualFinish>2015-09-22T17:00:00</ManualFinish><ManualDuration>PT48H0M0S</ManualDuration><DurationFormat>21</DurationFormat><Work>PT0H0M0S</Work><Stop>2015-09-15T08:43:12</Stop><Resume>2015-09-15T08:43:12</Resume><ResumeValid>0</ResumeValid><EffortDriven>0</EffortDriven><Recurring>0</Recurring><OverAllocated>0</OverAllocated><Estimated>0</Estimated><Milestone>0</Milestone><Summary>1</Summary><DisplayAsSummary>0</DisplayAsSummary><Critical>1</Critical><IsSubproject>0</IsSubproject><IsSubprojectReadOnly>0</IsSubprojectReadOnly><ExternalTask>0</ExternalTask><EarlyStart>2015-09-15T08:00:00</EarlyStart><EarlyFinish>2015-09-22T17:00:00</EarlyFinish><LateStart>2015-09-15T08:00:00</LateStart><LateFinish>2015-09-22T17:00:00</LateFinish><StartVariance>0</StartVariance><FinishVariance>0</FinishVariance><WorkVariance>0.00</WorkVariance><FreeSlack>0</FreeSlack><TotalSlack>0</TotalSlack><StartSlack>0</StartSlack><FinishSlack>0</FinishSlack><FixedCost>0</FixedCost><FixedCostAccrual>3</FixedCostAccrual><PercentComplete>16</PercentComplete><PercentWorkComplete>0</PercentWorkComplete><Cost>0</Cost><OvertimeCost>0</OvertimeCost><OvertimeWork>PT0H0M0S</OvertimeWork><ActualStart>2015-09-15T08:00:00</ActualStart><ActualDuration>PT7H29M18S</ActualDuration><ActualCost>0</ActualCost><ActualOvertimeCost>0</ActualOvertimeCost><ActualWork>PT0H0M0S</ActualWork><ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork><RegularWork>PT0H0M0S</RegularWork><RemainingDuration>PT40H30M42S</RemainingDuration><RemainingCost>0</RemainingCost><RemainingWork>PT0H0M0S</RemainingWork><RemainingOvertimeCost>0</RemainingOvertimeCost><RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork><ACWP>0.00</ACWP><CV>0.00</CV><ConstraintType>0</ConstraintType><CalendarUID>-1</CalendarUID><LevelAssignments>1</LevelAssignments><LevelingCanSplit>1</LevelingCanSplit><LevelingDelay>0</LevelingDelay><LevelingDelayFormat>8</LevelingDelayFormat><IgnoreResourceCalendar>0</IgnoreResourceCalendar><HideBar>0</HideBar><Rollup>0</Rollup><BCWS>0.00</BCWS><BCWP>0.00</BCWP><PhysicalPercentComplete>0</PhysicalPercentComplete><EarnedValueMethod>0</EarnedValueMethod><IsPublished>0</IsPublished><CommitmentType>0</CommitmentType></Task><Task><UID>3</UID><ID>1</ID><Name>Task 1</Name><Active>1</Active><Manual>1</Manual><Type>0</Type><IsNull>0</IsNull><CreateDate>2015-08-26T17:23:00</CreateDate><WBS>1</WBS><OutlineNumber>1</OutlineNumber><OutlineLevel>1</OutlineLevel><Priority>500</Priority><Start>2015-09-15T08:00:00</Start><Finish>2015-09-22T17:00:00</Finish><Duration>PT48H0M0S</Duration><ManualStart>2015-09-15T08:00:00</ManualStart><ManualFinish>2015-09-22T17:00:00</ManualFinish><ManualDuration>PT48H0M0S</ManualDuration><DurationFormat>7</DurationFormat><Work>PT0H0M0S</Work><Stop>2015-09-15T08:43:12</Stop><Resume>2015-09-15T08:43:12</Resume><ResumeValid>0</ResumeValid><EffortDriven>0</EffortDriven><Recurring>0</Recurring><OverAllocated>0</OverAllocated><Estimated>0</Estimated><Milestone>0</Milestone><Summary>0</Summary><DisplayAsSummary>0</DisplayAsSummary><Critical>1</Critical><IsSubproject>0</IsSubproject><IsSubprojectReadOnly>0</IsSubprojectReadOnly><ExternalTask>0</ExternalTask><EarlyStart>2015-09-15T08:00:00</EarlyStart><EarlyFinish>2015-09-22T17:00:00</EarlyFinish><LateStart>2015-09-15T08:00:00</LateStart><LateFinish>2015-09-22T17:00:00</LateFinish><StartVariance>0</StartVariance><FinishVariance>0</FinishVariance><WorkVariance>0.00</WorkVariance><FreeSlack>0</FreeSlack><TotalSlack>0</TotalSlack><StartSlack>0</StartSlack><FinishSlack>0</FinishSlack><FixedCost>0</FixedCost><FixedCostAccrual>3</FixedCostAccrual><PercentComplete>2</PercentComplete><PercentWorkComplete>0</PercentWorkComplete><Cost>0</Cost><OvertimeCost>0</OvertimeCost><OvertimeWork>PT0H0M0S</OvertimeWork><ActualStart>2015-09-15T08:00:00</ActualStart><ActualDuration>PT0H43M12S</ActualDuration><ActualCost>0</ActualCost><ActualOvertimeCost>0</ActualOvertimeCost><ActualWork>PT0H0M0S</ActualWork><ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork><RegularWork>PT0H0M0S</RegularWork><RemainingDuration>PT47H16M48S</RemainingDuration><RemainingCost>0</RemainingCost><RemainingWork>PT0H0M0S</RemainingWork><RemainingOvertimeCost>0</RemainingOvertimeCost><RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork><ACWP>0.00</ACWP><CV>0.00</CV><ConstraintType>0</ConstraintType><CalendarUID>-1</CalendarUID><LevelAssignments>1</LevelAssignments><LevelingCanSplit>1</LevelingCanSplit><LevelingDelay>0</LevelingDelay><LevelingDelayFormat>8</LevelingDelayFormat><IgnoreResourceCalendar>0</IgnoreResourceCalendar><HideBar>0</HideBar><Rollup>0</Rollup><BCWS>0.00</BCWS><BCWP>0.00</BCWP><PhysicalPercentComplete>0</PhysicalPercentComplete><EarnedValueMethod>0</EarnedValueMethod><IsPublished>1</IsPublished><CommitmentType>0</CommitmentType><TimephasedData><Type>11</Type><UID>3</UID><Start>2015-09-15T08:00:00</Start><Finish>2015-09-15T08:43:12</Finish><Unit>1</Unit><Value>1.5</Value></TimephasedData></Task><Task><UID>1</UID><ID>2</ID><Name>Task 2</Name><Active>1</Active><Manual>1</Manual><Type>0</Type><IsNull>0</IsNull><CreateDate>2015-08-26T17:23:00</CreateDate><WBS>2</WBS><OutlineNumber>2</OutlineNumber><OutlineLevel>1</OutlineLevel><Priority>500</Priority><Start>2015-09-21T08:00:00</Start><Finish>2015-09-21T17:00:00</Finish><Duration>PT8H0M0S</Duration><ManualStart>2015-09-21T08:00:00</ManualStart><ManualFinish>2015-09-21T17:00:00</ManualFinish><ManualDuration>PT8H0M0S</ManualDuration><DurationFormat>7</DurationFormat><Work>PT0H0M0S</Work><Stop>2015-09-21T10:24:00</Stop><Resume>2015-09-21T10:24:00</Resume><ResumeValid>0</ResumeValid><EffortDriven>0</EffortDriven><Recurring>0</Recurring><OverAllocated>0</OverAllocated><Estimated>0</Estimated><Milestone>0</Milestone><Summary>0</Summary><DisplayAsSummary>0</DisplayAsSummary><Critical>0</Critical><IsSubproject>0</IsSubproject><IsSubprojectReadOnly>0</IsSubprojectReadOnly><ExternalTask>0</ExternalTask><EarlyStart>2015-09-21T08:00:00</EarlyStart><EarlyFinish>2015-09-21T17:00:00</EarlyFinish><LateStart>2015-09-22T08:00:00</LateStart><LateFinish>2015-09-22T17:00:00</LateFinish><StartVariance>0</StartVariance><FinishVariance>0</FinishVariance><WorkVariance>0.00</WorkVariance><FreeSlack>4800</FreeSlack><TotalSlack>4800</TotalSlack><StartSlack>0</StartSlack><FinishSlack>4800</FinishSlack><FixedCost>0</FixedCost><FixedCostAccrual>3</FixedCostAccrual><PercentComplete>30</PercentComplete><PercentWorkComplete>0</PercentWorkComplete><Cost>0</Cost><OvertimeCost>0</OvertimeCost><OvertimeWork>PT0H0M0S</OvertimeWork><ActualStart>2015-09-21T08:00:00</ActualStart><ActualDuration>PT2H24M0S</ActualDuration><ActualCost>0</ActualCost><ActualOvertimeCost>0</ActualOvertimeCost><ActualWork>PT0H0M0S</ActualWork><ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork><RegularWork>PT0H0M0S</RegularWork><RemainingDuration>PT5H36M0S</RemainingDuration><RemainingCost>0</RemainingCost><RemainingWork>PT0H0M0S</RemainingWork><RemainingOvertimeCost>0</RemainingOvertimeCost><RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork><ACWP>0.00</ACWP><CV>0.00</CV><ConstraintType>0</ConstraintType><CalendarUID>-1</CalendarUID><LevelAssignments>1</LevelAssignments><LevelingCanSplit>1</LevelingCanSplit><LevelingDelay>0</LevelingDelay><LevelingDelayFormat>8</LevelingDelayFormat><IgnoreResourceCalendar>0</IgnoreResourceCalendar><HideBar>0</HideBar><Rollup>0</Rollup><BCWS>0.00</BCWS><BCWP>0.00</BCWP><PhysicalPercentComplete>0</PhysicalPercentComplete><EarnedValueMethod>0</EarnedValueMethod><IsPublished>1</IsPublished><CommitmentType>0</CommitmentType><TimephasedData><Type>11</Type><UID>1</UID><Start>2015-08-26T08:00:00</Start><Finish>2015-08-26T10:24:00</Finish><Unit>2</Unit><Value>30</Value></TimephasedData></Task><Task><UID>2</UID><ID>3</ID><Name>Task 3</Name><Active>1</Active><Manual>1</Manual><Type>0</Type><IsNull>0</IsNull><CreateDate>2015-08-26T17:23:00</CreateDate><WBS>3</WBS><OutlineNumber>3</OutlineNumber><OutlineLevel>1</OutlineLevel><Priority>500</Priority><Start>2015-09-18T08:00:00</Start><Finish>2015-09-22T17:00:00</Finish><Duration>PT24H0M0S</Duration><ManualStart>2015-09-18T08:00:00</ManualStart><ManualFinish>2015-09-22T17:00:00</ManualFinish><ManualDuration>PT24H0M0S</ManualDuration><DurationFormat>7</DurationFormat><Work>PT0H0M0S</Work><Stop>2015-09-21T09:21:36</Stop><Resume>2015-09-21T09:21:36</Resume><ResumeValid>0</ResumeValid><EffortDriven>0</EffortDriven><Recurring>0</Recurring><OverAllocated>0</OverAllocated><Estimated>0</Estimated><Milestone>0</Milestone><Summary>0</Summary><DisplayAsSummary>0</DisplayAsSummary><Critical>1</Critical><IsSubproject>0</IsSubproject><IsSubprojectReadOnly>0</IsSubprojectReadOnly><ExternalTask>0</ExternalTask><EarlyStart>2015-09-18T08:00:00</EarlyStart><EarlyFinish>2015-09-22T17:00:00</EarlyFinish><LateStart>2015-09-18T08:00:00</LateStart><LateFinish>2015-09-22T17:00:00</LateFinish><StartVariance>0</StartVariance><FinishVariance>0</FinishVariance><WorkVariance>0.00</WorkVariance><FreeSlack>0</FreeSlack><TotalSlack>0</TotalSlack><StartSlack>0</StartSlack><FinishSlack>0</FinishSlack><FixedCost>0</FixedCost><FixedCostAccrual>3</FixedCostAccrual><PercentComplete>39</PercentComplete><PercentWorkComplete>0</PercentWorkComplete><Cost>0</Cost><OvertimeCost>0</OvertimeCost><OvertimeWork>PT0H0M0S</OvertimeWork><ActualStart>2015-09-18T08:00:00</ActualStart><ActualDuration>PT9H21M36S</ActualDuration><ActualCost>0</ActualCost><ActualOvertimeCost>0</ActualOvertimeCost><ActualWork>PT0H0M0S</ActualWork><ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork><RegularWork>PT0H0M0S</RegularWork><RemainingDuration>PT14H38M24S</RemainingDuration><RemainingCost>0</RemainingCost><RemainingWork>PT0H0M0S</RemainingWork><RemainingOvertimeCost>0</RemainingOvertimeCost><RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork><ACWP>0.00</ACWP><CV>0.00</CV><ConstraintType>0</ConstraintType><CalendarUID>-1</CalendarUID><LevelAssignments>1</LevelAssignments><LevelingCanSplit>1</LevelingCanSplit><LevelingDelay>0</LevelingDelay><LevelingDelayFormat>8</LevelingDelayFormat><IgnoreResourceCalendar>0</IgnoreResourceCalendar><HideBar>0</HideBar><Rollup>0</Rollup><BCWS>0.00</BCWS><BCWP>0.00</BCWP><PhysicalPercentComplete>0</PhysicalPercentComplete><EarnedValueMethod>0</EarnedValueMethod><IsPublished>1</IsPublished><CommitmentType>0</CommitmentType><TimephasedData><Type>11</Type><UID>2</UID><Start>2015-08-26T08:00:00</Start><Finish>2015-08-27T08:00:00</Finish><Unit>2</Unit><Value>36.91</Value></TimephasedData><TimephasedData><Type>11</Type><UID>2</UID><Start>2015-08-27T08:00:00</Start><Finish>2015-08-27T09:21:36</Finish><Unit>2</Unit><Value>5.67</Value></TimephasedData></Task></Tasks><Resources><Resource><UID>0</UID><ID>0</ID><Type>1</Type><IsNull>0</IsNull><WorkGroup>0</WorkGroup><MaxUnits>1.00</MaxUnits><PeakUnits>0.00</PeakUnits><OverAllocated>0</OverAllocated><CanLevel>1</CanLevel><AccrueAt>3</AccrueAt><Work>PT0H0M0S</Work><RegularWork>PT0H0M0S</RegularWork><OvertimeWork>PT0H0M0S</OvertimeWork><ActualWork>PT0H0M0S</ActualWork><RemainingWork>PT0H0M0S</RemainingWork><ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork><RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork><PercentWorkComplete>0</PercentWorkComplete><StandardRate>0</StandardRate><StandardRateFormat>2</StandardRateFormat><Cost>0</Cost><OvertimeRate>0</OvertimeRate><OvertimeRateFormat>2</OvertimeRateFormat><OvertimeCost>0</OvertimeCost><CostPerUse>0</CostPerUse><ActualCost>0</ActualCost><ActualOvertimeCost>0</ActualOvertimeCost><RemainingCost>0</RemainingCost><RemainingOvertimeCost>0</RemainingOvertimeCost><WorkVariance>0.00</WorkVariance><CostVariance>0</CostVariance><SV>0.00</SV><CV>0.00</CV><ACWP>0.00</ACWP><CalendarUID>2</CalendarUID><BCWS>0.00</BCWS><BCWP>0.00</BCWP><IsGeneric>0</IsGeneric><IsInactive>0</IsInactive><IsEnterprise>0</IsEnterprise><BookingType>0</BookingType><CreationDate>2015-08-26T17:23:00</CreationDate><IsCostResource>0</IsCostResource><IsBudget>0</IsBudget></Resource></Resources><Assignments><Assignment><UID>1</UID><TaskUID>1</TaskUID><ResourceUID>-65535</ResourceUID><PercentWorkComplete>30</PercentWorkComplete><ActualCost>0</ActualCost><ActualOvertimeCost>0</ActualOvertimeCost><ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork><ActualStart>2015-09-21T08:00:00</ActualStart><ActualWork>PT2H24M0S</ActualWork><ACWP>0.00</ACWP><Confirmed>0</Confirmed><Cost>0</Cost><CostRateTable>0</CostRateTable><RateScale>0</RateScale><CostVariance>0</CostVariance><CV>-0.00</CV><Delay>0</Delay><Finish>2015-09-21T17:00:00</Finish><FinishVariance>0</FinishVariance><WorkVariance>0.00</WorkVariance><HasFixedRateUnits>1</HasFixedRateUnits><FixedMaterial>0</FixedMaterial><LevelingDelay>0</LevelingDelay><LevelingDelayFormat>7</LevelingDelayFormat><LinkedFields>0</LinkedFields><Milestone>0</Milestone><Overallocated>0</Overallocated><OvertimeCost>0</OvertimeCost><OvertimeWork>PT0H0M0S</OvertimeWork><RegularWork>PT8H0M0S</RegularWork><RemainingCost>0</RemainingCost><RemainingOvertimeCost>0</RemainingOvertimeCost><RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork><RemainingWork>PT5H36M0S</RemainingWork><ResponsePending>0</ResponsePending><Start>2015-09-21T08:00:00</Start><Stop>2015-09-21T10:24:00</Stop><Resume>2015-09-21T10:24:00</Resume><StartVariance>0</StartVariance><Units>1</Units><UpdateNeeded>0</UpdateNeeded><VAC>0.00</VAC><Work>PT8H0M0S</Work><WorkContour>0</WorkContour><BCWS>0.00</BCWS><BCWP>-0.00</BCWP><BookingType>0</BookingType><CreationDate>2015-08-26T17:23:00</CreationDate><BudgetCost>0</BudgetCost><BudgetWork>PT0H0M0S</BudgetWork><TimephasedData><Type>1</Type><UID>1</UID><Start>2015-09-21T10:24:00</Start><Finish>2015-09-21T17:00:00</Finish><Unit>2</Unit><Value>PT5H36M0S</Value></TimephasedData><TimephasedData><Type>2</Type><UID>1</UID><Start>2015-09-21T08:00:00</Start><Finish>2015-09-21T10:24:00</Finish><Unit>2</Unit><Value>PT2H24M0S</Value></TimephasedData></Assignment><Assignment><UID>2</UID><TaskUID>2</TaskUID><ResourceUID>-65535</ResourceUID><PercentWorkComplete>39</PercentWorkComplete><ActualCost>0</ActualCost><ActualOvertimeCost>0</ActualOvertimeCost><ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork><ActualStart>2015-09-18T08:00:00</ActualStart><ActualWork>PT9H21M36S</ActualWork><ACWP>0.00</ACWP><Confirmed>0</Confirmed><Cost>0</Cost><CostRateTable>0</CostRateTable><RateScale>0</RateScale><CostVariance>0</CostVariance><CV>-0.00</CV><Delay>0</Delay><Finish>2015-09-22T17:00:00</Finish><FinishVariance>0</FinishVariance><WorkVariance>0.00</WorkVariance><HasFixedRateUnits>1</HasFixedRateUnits><FixedMaterial>0</FixedMaterial><LevelingDelay>0</LevelingDelay><LevelingDelayFormat>7</LevelingDelayFormat><LinkedFields>0</LinkedFields><Milestone>0</Milestone><Overallocated>0</Overallocated><OvertimeCost>0</OvertimeCost><OvertimeWork>PT0H0M0S</OvertimeWork><RegularWork>PT24H0M0S</RegularWork><RemainingCost>0</RemainingCost><RemainingOvertimeCost>0</RemainingOvertimeCost><RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork><RemainingWork>PT14H38M24S</RemainingWork><ResponsePending>0</ResponsePending><Start>2015-09-18T08:00:00</Start><Stop>2015-09-21T09:21:36</Stop><Resume>2015-09-21T09:21:36</Resume><StartVariance>0</StartVariance><Units>1</Units><UpdateNeeded>0</UpdateNeeded><VAC>0.00</VAC><Work>PT24H0M0S</Work><WorkContour>0</WorkContour><BCWS>0.00</BCWS><BCWP>-0.00</BCWP><BookingType>0</BookingType><CreationDate>2015-08-26T17:23:00</CreationDate><BudgetCost>0</BudgetCost><BudgetWork>PT0H0M0S</BudgetWork><TimephasedData><Type>1</Type><UID>2</UID><Start>2015-09-21T09:21:36</Start><Finish>2015-09-22T09:21:36</Finish><Unit>2</Unit><Value>PT8H0M0S</Value></TimephasedData><TimephasedData><Type>1</Type><UID>2</UID><Start>2015-09-22T09:21:36</Start><Finish>2015-09-22T17:00:00</Finish><Unit>2</Unit><Value>PT6H38M24S</Value></TimephasedData><TimephasedData><Type>2</Type><UID>2</UID><Start>2015-09-18T08:00:00</Start><Finish>2015-09-19T08:00:00</Finish><Unit>2</Unit><Value>PT8H0M0S</Value></TimephasedData><TimephasedData><Type>2</Type><UID>2</UID><Start>2015-09-19T08:00:00</Start><Finish>2015-09-20T08:00:00</Finish><Unit>2</Unit><Value></Value></TimephasedData><TimephasedData><Type>2</Type><UID>2</UID><Start>2015-09-20T08:00:00</Start><Finish>2015-09-21T08:00:00</Finish><Unit>2</Unit><Value></Value></TimephasedData><TimephasedData><Type>2</Type><UID>2</UID><Start>2015-09-21T08:00:00</Start><Finish>2015-09-21T09:21:36</Finish><Unit>2</Unit><Value>PT1H21M36S</Value></TimephasedData></Assignment><Assignment><UID>3</UID><TaskUID>3</TaskUID><ResourceUID>-65535</ResourceUID><PercentWorkComplete>2</PercentWorkComplete><ActualCost>0</ActualCost><ActualOvertimeCost>0</ActualOvertimeCost><ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork><ActualStart>2015-09-15T08:00:00</ActualStart><ActualWork>PT0H43M12S</ActualWork><ACWP>0.00</ACWP><Confirmed>0</Confirmed><Cost>0</Cost><CostRateTable>0</CostRateTable><RateScale>0</RateScale><CostVariance>0</CostVariance><CV>-0.00</CV><Delay>0</Delay><Finish>2015-09-22T17:00:00</Finish><FinishVariance>0</FinishVariance><WorkVariance>0.00</WorkVariance><HasFixedRateUnits>1</HasFixedRateUnits><FixedMaterial>0</FixedMaterial><LevelingDelay>0</LevelingDelay><LevelingDelayFormat>7</LevelingDelayFormat><LinkedFields>0</LinkedFields><Milestone>0</Milestone><Overallocated>0</Overallocated><OvertimeCost>0</OvertimeCost><OvertimeWork>PT0H0M0S</OvertimeWork><RegularWork>PT48H0M0S</RegularWork><RemainingCost>0</RemainingCost><RemainingOvertimeCost>0</RemainingOvertimeCost><RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork><RemainingWork>PT47H16M48S</RemainingWork><ResponsePending>0</ResponsePending><Start>2015-09-15T08:00:00</Start><Stop>2015-09-15T08:43:12</Stop><Resume>2015-09-15T08:43:12</Resume><StartVariance>0</StartVariance><Units>1</Units><UpdateNeeded>0</UpdateNeeded><VAC>0.00</VAC><Work>PT48H0M0S</Work><WorkContour>0</WorkContour><BCWS>0.00</BCWS><BCWP>-0.00</BCWP><BookingType>0</BookingType><CreationDate>2015-08-26T17:23:00</CreationDate><BudgetCost>0</BudgetCost><BudgetWork>PT0H0M0S</BudgetWork><TimephasedData><Type>1</Type><UID>3</UID><Start>2015-09-15T08:43:12</Start><Finish>2015-09-16T08:43:12</Finish><Unit>2</Unit><Value>PT8H0M0S</Value></TimephasedData><TimephasedData><Type>1</Type><UID>3</UID><Start>2015-09-16T08:43:12</Start><Finish>2015-09-17T08:43:12</Finish><Unit>2</Unit><Value>PT8H0M0S</Value></TimephasedData><TimephasedData><Type>1</Type><UID>3</UID><Start>2015-09-17T08:43:12</Start><Finish>2015-09-18T08:43:12</Finish><Unit>2</Unit><Value>PT8H0M0S</Value></TimephasedData><TimephasedData><Type>1</Type><UID>3</UID><Start>2015-09-18T08:43:12</Start><Finish>2015-09-19T08:43:12</Finish><Unit>2</Unit><Value>PT7H16M48S</Value></TimephasedData><TimephasedData><Type>1</Type><UID>3</UID><Start>2015-09-19T08:43:12</Start><Finish>2015-09-20T08:43:12</Finish><Unit>2</Unit><Value></Value></TimephasedData><TimephasedData><Type>1</Type><UID>3</UID><Start>2015-09-20T08:43:12</Start><Finish>2015-09-21T08:43:12</Finish><Unit>2</Unit><Value>PT0H43M12S</Value></TimephasedData><TimephasedData><Type>1</Type><UID>3</UID><Start>2015-09-21T08:43:12</Start><Finish>2015-09-22T08:43:12</Finish><Unit>2</Unit><Value>PT8H0M0S</Value></TimephasedData><TimephasedData><Type>1</Type><UID>3</UID><Start>2015-09-22T08:43:12</Start><Finish>2015-09-22T17:00:00</Finish><Unit>2</Unit><Value>PT7H16M48S</Value></TimephasedData><TimephasedData><Type>2</Type><UID>3</UID><Start>2015-09-15T08:00:00</Start><Finish>2015-09-15T08:43:12</Finish><Unit>1</Unit><Value>PT0H43M12S</Value></TimephasedData></Assignment></Assignments></Project>
Now want to add Task 1.1 Under Task 1 (a new sub Task under Task 1) using Project XML Import.
Project XML created to insert Task 1.1 is as follows.
For the new Task the next UID is used. In this case this is 4. The Task.ID is inserted – for this new task it is 2 and for subsequent tasks the Task.ID is incremented by 1.
<?xml version="1.0" encoding="UTF-8" standalone="yes"?><Project xmlns="http://schemas.microsoft.com/project"><SaveVersion>14</SaveVersion><Name>ProjectImportTest.xml</Name><Title>ProjectImportTest</Title><Company>c</Company><Author>Author, Project</Author><Tasks><Task><UID>0</UID><ID>0</ID><Name>ProjectImportTest</Name><Manual>0</Manual><CreateDate>2015-08-26T17:23:00</CreateDate><WBS>0</WBS><OutlineNumber>0</OutlineNumber><OutlineLevel>0</OutlineLevel><Start>2015-09-15T08:00:00</Start><Finish>2015-09-22T17:00:00</Finish><Duration>PT48H0M0S</Duration></Task><Task><UID>3</UID><ID>1</ID><Name>Task 1</Name><Manual>0</Manual><CreateDate>2015-08-26T17:23:00</CreateDate><WBS>1</WBS><OutlineNumber>1</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2015-09-15T08:00:00</Start><Finish>2015-09-22T17:00:00</Finish><Duration>PT48H0M0S</Duration></Task><Task><UID>4</UID><ID>2</ID><Name>Task 1.1</Name><Manual>0</Manual><CreateDate>2015-08-26T17:23:00</CreateDate><WBS>1.1</WBS><OutlineNumber>1.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Start>2015-09-15T08:00:00</Start><Finish>2015-09-17T17:00:00</Finish><Duration>3d</Duration></Task><Task><UID>1</UID><ID>3</ID><Name>Task 2</Name><Manual>0</Manual><CreateDate>2015-08-26T17:23:00</CreateDate><WBS>2</WBS><OutlineNumber>2</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2015-09-21T08:00:00</Start><Finish>2015-09-21T17:00:00</Finish><Duration>PT8H0M0S</Duration></Task><Task><UID>2</UID><ID>4</ID><Name>Task 3</Name><Manual>0</Manual><CreateDate>2015-08-26T17:23:00</CreateDate><WBS>3</WBS><OutlineNumber>3</OutlineNumber><OutlineLevel>1</OutlineLevel><Start>2015-09-18T08:00:00</Start><Finish>2015-09-22T17:00:00</Finish><Duration>PT24H0M0S</Duration></Task></Tasks></Project>
This XML is imported to the active Project (Currently Opened) with Merge Option. [Merge the data into active Project]
<Image 2>
After Import the new Task is appended at the end.
The OutlineNumber for the new Task in the XML file is ignored and it is automatically set to 3.1.
<Image 3>
How to create Project XML so that this task is inserted.
<Image 4>
Same question for deleting any task from the Existing Project.
For example if a Project Contains 10 different Tasks and Each task has 3 sub tasks, then is it possible to delete the 2<sup>nd</sup> sub task of Task # 6 using XML import with Option ”Merge the Data into Active Project”.