Critical Chain in MS project

Hello,

project plan will only realistic when it all tasks are schedules with proper resources. As availability of resources may vary during project and it may impact project delivery date as well identifying critical tasks.

while measuring critical path, we generally focus on tasks only without assignment of resources but in reality it does not happen when resources are limited and shared. after assigning resources on each task (where resources are shared), critical path of MS project 2010 will only consider those task as critical which has 0 slack. that does not represent real critical path with resources.

Please suggest how to make critical patch with shared resources in MS project 2010.

Utk 