Quantcast
Channel: Project Customization and Programming forum
Viewing all articles
Browse latest Browse all 5347

Auto update a project once its affected by a cross project dependency - Project Online

$
0
0

i'm using the ‘links between projects’ feature.  For example:  I link ‘Task 5 in ‘Project A’ to ‘Task 1’ in ‘Project B’.

The project manager then opens ‘Project A’.  makes various changes to the schedule which in turn, pushes out ‘Task 5’, and therefore ‘Task 1’ has also been pushed out within ‘Project B’

The problem is this:  When ‘Project A’ is published, ‘Project B’ does not push out.  I understand that this is because the system is designed that Project B needs to be opened, and then published before the changes are reflected in the ‘publish’ tables (and therefore visible in the project center)

I need to find a way to automate this process.  So when ‘Project A’ is pushed out, and ‘Project B’ is impacted, Project B is automatically pushed out.

Thanks in advance.


Viewing all articles
Browse latest Browse all 5347

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>