Hi all! 1st ly I want to thank the contributors to this forum i have been saved by this forum a few times.
This is concerning MS project 2010, the kind of planning I do is effort driven with resource for each task. After linking my task I go to Resource sheet, check Detail and then select Resource Graph and then MS project 2010 will display the manpower histogram.
However I want to be able to extract the actual data that created this histogram. I couldn't find any functon to do that so I presume that I will have to use VBA to do it. I have search for the right object and method to use to do this but I couldn't find what I want. Can someone please let me know the object and methods to use to get what I need??? Or whatever method to get the data out. Thanks.
The ideal data is something like this
A(x:1)-->Date
A(x:2)-->manpower.
I think you get the picture.