I have a Ms Project file for a project at hand. I have created a calendar that defines 3 month period as non-working in Enterprise. I applied/assigned the calendar to a few tasks in the project. The links and the dates get rescheduled correctly. However, as soon as I publish the file to PWA, the calendar icon disappears and when I reopen the file no trace of the calendar that was assigned can be found..
Any help or suggestion with this regard is much appreciated!