Hi, I want to export from Navision to Ms Project, I'm using the 'Microsoft
Office Project 15.0 Object Library'.Application , I have no problem creating the Project, creating tasks, but my problem is that if I create a task with a duration of 15 days and try to insert splits in it it automatically rearrange the task so it changes
my duration, I suppose there should be some tip to do this. I need to insert tasks with splits in it, how you would do it?
luis molina