Mass update of cost rate tables and effective dates?

$
0
0

We are starting to forecast finances for schedules into 2013 and beyond in MSPS 2010.  We need to put in the 2013 rates with effective dates of 1/1/13 so the new rates are applied on about 900 resources.  I've seen the thread here which asked about the exact same thing a couple of years ago but it wasn't much help.

Suggestion was made on the Project Server - Setup, Upgrade, Administration and Operation forum that I post here to see if anyone had a VBA solution to this process.

Thanks for any ideas!

DJ