For some quick context: I am the Project Engineer for a masonry company and my boss likes to see how much over/under budget we are, etc.
This has been driving me crazy- I have created a custom report to show our actual % work completed graphed alongside cumulative cost.
The issue is that there is only a value for % complete which we all know is not the same as % work completed. It is showing that we are 40% done with the job on the chart but I know based on the % Work Complete value that the actual work on the project that is done is 9% (we are going to be putting more men on the job so it makes the duration and work done ratio way off).
I am unsure if I'm just not seeing it or if it legitimately is not an option to add to my chart?
Any help is very much appreciated, even if it's a complex work-around.