Good Afternoon,
I'm hoping that someone may know the solution to this one because I'm sure it must be possible.
I want to be able to set up tasks to automatically schedule themselves in calendar days (including weekends) but add in a 'constraint' to prevent tasks from ending on a weekend or a Monday (and if necessary extend the task duration to accommodate this).
Does anyone know if this is possible?
Thanks very much