In my project plan in MS project 2010, there are two independent task which are done by same resource. lets say (A and B tasks). task A comes in initial stage of planing while task B comes at later stage in planning. but task need to be done first due
to some reason. as these two task are independent, I can not show dependency. I tried to increase priority of task B but still task A is scheduled first. How can I make task B to be scheduled earlier than task A?
↧