I'm working in only Project 2010 (not professional, not server). I need to make a work schedule for our 2nd team, which will be working 7 p.m. to 7 a.m. Our work week starts on Sunday at 7 p.m. for this team and runs thru Saturday night. Please let me
know how I can make a schedule under the Change Working Time area of Project 2010. I'm so frustrated!
↧