Hi
To my surprise this one seem to have me a bit stumped.
What I am after is a way of looking at all projects in project centre and then break them down by task.
I would then filter that view so that the information is not excessive and I would cstomise a barchart set to give me visual results. I am actually going to use it to look at remianing work against baseline work filtered using some custome criteria but I cannot even work out how to get started :-(
It should look something like this;
Basline Work ETC
Project A 60 5 | [_________________]
Task 1 10 0 | ____________
Task 2 50 5 |
______
Project B etc |[____________________]
Task 1 |
______
Task 2 | ___________
Task 3 | ______
Can anyone point me in the right direction?
Thanks