Resource utilization report

$
0
0

Dear Project Server users,

I want to create a report that measures a team's utilization, using powerpivot and with the information from the SQL PWA database.

Basically, I want to measure how big a resource's utilization for a period (week, month, quarter, year) is.

Resource utilization is measured by dividing the time a resource spends on a project (per a period) with the total work time (for the same period).

I see that there is a total work field in timesheets, but I cannot find it in the database. Is there a way to call this field from a base? Can anyone propose a quick and elegant solution?

 With best regards,
Petar 