Dear All,
I asked this before in another thread:
http://social.technet.microsoft.com/Forums/en-US/projectprofessional2010general/thread/84c9e718-51b3-466b-a351-fabd86aa2f02/
I want to create a macro that create either, a msgbox with a hint or a column with a hint: that a resource is working on a parallel task at the moment.
For example: I have a schedule (in MS-Project 2003) and if I move a task because of some technical reasons from one week to another, the macro should check after moving the task, if the resource on that task is also invited to another task at the same time (must not be overloaded, even if he works on a parallel task, even if that is only for 1 hour).
The hint could be something like: "Be careful! Resource XY is also working at that time on task 41".
Is that in any way possible to do something like that?
I am very happy about any kind of help.
Best regards,
Toby