MS Project Server 2007 - Ordering Resources from Reporting DB as shown on Project Pro Task Form

$
0
0

With help from this forum I was able to create a SQL Server view from the Reporting DB that concatenated the ResourceInitials for each task. What I need to do now is concatenate them in the specific order that is shown on the Project Professional 2007 Task Form window.  Is there a Resource order field somewhere in the Reporting DB that can say what order they are listed?

For example, in the Project Pro Task Form, a planner has listed the Resources in a specific order:

ID    Resource Name        Units      Work

71   Joey Smith                 100%     8h

36   Rahim Moya               100%     8h

25   Dee Thompson           100%    8h

When I concatenate them, the Resources come out in a random order (such as RM, DT, JS) and not as the planner input them. Is there somewhere in the database that will tell me what order the resources are in?

The code I used for concatenation was in this Forum under the question: Task "Resource Initials" list from Reporting DB in Project Server 2007?

Any help you could provide would be much appreciated.