Hello everyone,
I am currently trying to update the TS actuals in a pre-existing timesheet that already has timesheet lines in them. I was wondering whether this was possible via the PSI, as I have checked the forms for someone having a similar problem and it seems like no one has had success.
I need to know whether or not it is possible to load a pre-existing timesheet into the timesheet object and then edit the actuals in a line based on the TSLUID, then send it into the queue via TimesheetLineUpdate method.
I have tried following a previous thread for a person who had a similar question, and I ended up with the same exact problems as well.
http://social.msdn.microsoft.com/Forums/en-AU/project2010custprog/thread/59b5ca3b-8fd2-488d-aded-52502e23a74d
I was wondering whether anyone has successfully done this?
We are using Project Server 2010 PSI, to programmatically edit the actual of a timesheet line within a timesheet.