Analyze different projects in Visual Reports

$
0
0

Hi

I have a resource pool with several projects. When I create the master file I want to use Visual Reports to among other things check timephased costs for each project but in the available fields I dont find Project.

n the master file the project files are linked so I tried to customize Text1 to show the name of the projects in Task usage. But that doesnt work for tasks. In Resource usage I can do that but Text1 displaysResource pool. And that is natural since they reside in that file. And this happens even if I unlink the Resource pool.

So my question is - is there a way to see timphased costs for each project in Visual Reports?

Or do I have to use SQL to get these data?