I have a share resouce pool file called Resource_Pool.mpp.
It has no tasks, just the resource information.
I have other files that use the shared resource pool file. I have tasks and allocations in those files.
When I open the Resource_Pool file and look at the Resource Usage view, I see the allocations from the other projects files in the Project Column. Unfortunaltely, the other projects are shown with the full path in their name so they look like c:\users\flyboy54\documents\business\projects\boards\project_415.mpp.
Is there a way to show them with just project_415.mpp?