I am using MS Project Professional 2013 to manage an Engineering Departments workload using a trial version of 2013 for proof of concept. I have several user defined fields (Text 1 - 5). I also use the WBS field to establish a unique identifier for a group of subtasks.
I want to use the upcoming task report to generate a task list that shows tasks that should be in work during a two day window. I have set my report parameters up, but when I try and use the filter to return items which should start between two dates, the report does not show any actual filtering. What am I missing.