I'm having problems getting the right, calculated start date. All new tasks start at 19-12-13. However, the project start date is 26-6-13. If I enter a SS dependency with a task that starts for example on 16-8-13, the start date still doesn't change. The advanced tab says there is no deadline and the constraint type is "ASAP".
What am I doing wrong?